The contractor finished up 2 days of paving on 8/25. This is showing the final bit of paving to be completed. Looks nice! Next up: exterior fencing the week of Aug 31. Hoping for sports court work about mid-Sept but don’t know the exact date yet. The light poles in the middle will remain in this latest change and we will evaluate the lighting for play after the courts are finished.
Monthly Archives: August 2020
LBCC Courts Update – 8/11/2020
Construction restarted on 8/10 after almost 2 months because of a major design change. Chain link fencing is down. The tennis net posts were removed and holes refilled and asphalted. Porta potty/shed pad excavated and backfilled with aggregate. Short sidewalk and water fountain area excavated and backfilled with aggregate. The existing fence along the North side is remaining.